London Array Wind Farm
6:18 AM
Posted by Energetic
The first phase of London Array Wind Farm will consist of 175 SWT-3.6 turbines and two offshore substations. All turbines and also offshore substations will be erected on 177 monopiles. In addition, the first stage includes 220 kilometres (140 mi) of 150 kV subsea export cable connecting the offshore substations to the shore and 210 kilometres (130 mi) of 33 kV array cables to link the turbines to each other and to the offshore substations and a new onshore substation near Graveney on the north Kent coast.
The proposers say this is enough to power a quarter of the homes in Greater London or the entire counties of Kent and East Sussex.
The Wind Turbines will be supplied by Siemens Wind Power. Their foundations are built by the joint venture between Per Aarsleff and Bilfinger Berger Ingenieurbau. The same company supply and install monopiles. Generators will be installed by MPI and A2SEA by using an installation vessel MPI Adventure and a jack-up barge Sea Worker. Two offshore substations will be designed, fabricated and installed by Future Energy, a joint venture between Fabricom, Iemants and Geosea, while electrical systems and onshore substation work will be undertaken by Siemens Transmission & Distribution. The subsea export cable will supply by Nexans and array cables by JDR Cable Systems. The array cables will be installed by Global Marine Systems and the export cables will be installed by VSMC.
Ownership is 50% DONG Energy, 30% E.ON UK Renewables and 20% Masdar. The wind farm was planned to be built by London Array Limited, a consortium of Shell WindEnergy Ltd, E.ON UK Renewables and DONG Energy. In May 2008, Shell announced that it was pulling out of the project. It was announced in July 2008 that E.ON UK and DONG Energy would buy Shell's stake. Subsequently on 16 October 2008, London Array announced the Abu Dhabi-based Masdar would join E.ON as a joint venture party in the scheme. Under the agreement, Masdar purchased 40% of E.ON's half share of the scheme, giving Masdar a 20% stake in the project overall.
In March 2009, the backers agreed on an initial investment of €2.2 billion. Offshore work is due to started in February 2011 and the proposed completion date for the first stage is in 2012. The second stage (bringing the revised total to 217 turbines) will add enough capacity to generate 1,000 MW for 750,000 homes. Financing of phase 1 have been achieved through the European Investment Bank and Danish Export Credit Fund with £250 million.
London Array Offshore Wind Farm | |
---|---|
Country | England, United Kingdom |
Locale | 7 miles (11 km) off North Foreland, Kent |
Status | Under construction |
Construction began | March 2011 |
Commission date | 2012 (expected) |
Owner(s) | DONG Energy (50%) E.ON UK Renewables (30%) Masdar (20%) |
Developer(s) | London Array Limited |
Turbine information | |
Turbines | 341 x 3.6MW |
Manufacturer(s) | Siemens Wind Power |
Wind farm information | |
Distance from shore | 7 mi (11 km) |
Power generation information | |
Maximum capacity | 1,000 MW |