Crookwell Wind Farm

Crookwell Wind Farm, located at Crookwell west of Goulburn, New South Wales, consists of eight 600 kW wind turbines giving a total capacity of 4.8 MW. It was the first grid-connected wind farm in Australia when built by Pacific Power in 1998. It is now owned by Eraring Energy, and the wind farm currently supplies electricity to Country Energy's "GreenPower" customers.

Phase two of the Crookwell Wind Farm, which will have an installed capacity of 92 MW, is under construction as of 2009 and will cost $238 million.

Crookwell Wind Farm
Country Australia
Locale Crookwell, New South Wales
Status Operational
Commission date 1998
Owner(s) Pacific Power

Turbine information
Turbines 8 X 600 kW
Wind farm information
Type onshore

Power generation information
Installed capacity 4.8 MW
Maximum capacity 92 MW